山东电力建设第三工程有限公司-pg娱乐电子游戏平台

welcome to sepcoiii !

jiuquan ruineng subei gancaoquan 1-d phase i 100mw wind power project was connected to the grid with full capacity

2023-12-20 14:25:59

at 15:22 on december 19, jiuquan ruineng subei gancaoquan 1-d phase i 100mw wind power project was connected to the grid with full capacity.

the project is located in mazongshan town, subei mongolian autonomous county, jiuquan city. the total installed capacity of the project is 100mw. it is designed to install 22 sl4550/172/105 wind turbines with a single unit capacity of 4.55 mw. the total length of the 35 kv collector line in the site is 26.9 km, and the total length of the 110kv booster station outgoing line is 30.7 km. after the project is connected to the grid for power generation, the annual equivalent full-load utilization hours are 3149 hours, and the annual on-grid energy is 314900 mwh.

since the project was officially started on june 26, 2022, the project execution team has overcome the difficulties of raw materials, commercial concrete, wind turbine equipment entering the site, tight construction period, harsh weather conditions and other unfavorable factors, giv en full play to organizational and professional advantages, increased communication with wind turbine manufacturers, operation and maintenance personnel and technical personnel, and ensured all aspects. it lays a solid foundation for the smooth realization of the goal of grid-connected power generation. at the same time, the meticulous and excellent working attitude of the project execution team has also won the unanimous praise of the owners and supervisors.

网站地图